Electrical maintenance contracts: what to specify and compare

Most sites have electrical maintenance arranged; fewer can produce the records when asked. Here is what to put in the specification before you compare quotes.

Electrician in hard hat and safety glasses working on a switchboard

Most commercial and industrial sites have some form of electrical maintenance arranged. Far fewer can produce, on the day an auditor or insurer asks, a current list of what was tested, by whom, with what result and when the next visit is due. That gap is usually a specification problem rather than a contractor problem: the contract was priced on a visit count instead of an outcome.

If you are putting electrical maintenance out to market, or renewing an arrangement you inherited, the points below are worth settling in writing. They are also what makes two quotes comparable, which is harder than it sounds when one includes testing records and the other does not.

Start with the asset register, not the price

A price per visit tells you nothing until both sides agree what is being maintained. Write down the assets first: main switchboard and every distribution board, sub-mains, the safety switches protecting each board, plug-in equipment by area, emergency and exit fittings, and dedicated plant supplies such as compressors or pumps. Note what is base-building and what belongs to a tenant, because that line decides who pays and who receives the records.

Then require the register to be maintained as a contract deliverable, not kept only in the contractor’s system. Equipment arrives, moves and gets scrapped, and a register nobody updates quietly stops matching the site. Our own maintenance contracts are built this way for that reason.

Set intervals by environment, not by habit

A single site-wide interval is the most common weakness in an inherited contract. SafeWork NSW frames the duty narrowly: a business or other PCBU must make sure electrical equipment is regularly inspected and tested by a competent person where it is supplied through a socket outlet and used in conditions likely to damage it or shorten its life – moisture, heat, vibration, mechanical damage, corrosive chemicals or dust. A dispatch area and a first-floor office are not the same environment.

It also notes that the appropriate frequency varies with the nature of the workplace and the risks, and points to AS/NZS 3760 for inspection, testing and tagging methods and frequency. So ask a contractor to propose intervals area by area and justify them, rather than quoting one number for the building. We have written separately about how those intervals are worked out.

Say who the competent person is

"Competent person" is doing a lot of work in that duty. SafeWork NSW describes it as someone who has acquired, through training, qualification or experience, the knowledge and skills to carry out the inspection and testing, and who has the proper testing equipment. Separately, any electrical wiring work in NSW must be done by or under the supervision of a licensed electrician.

In practice that means asking a tenderer two questions: who will actually attend, and what licence or qualification sits behind each task. The answer often explains a price difference.

Agree the isolation window before you sign

This is the clause that gets written after the first argument instead of before it. SafeWork NSW is direct that electrical work must not be carried out on energised electrical equipment, and that live work is prohibited except in a small set of circumstances, each with added controls including a safe work method statement and a competent person. It also requires that de-energised circuits cannot be inadvertently re-energised, which is why lock-out and tag-out procedures appear on site.

For a maintenance contract, that means three practical items:

  • When boards can be opened and isolated, and how much notice is needed
  • Who on your side authorises an isolation, and who is told before power goes off
  • Which tasks need no outage – a thermal scan is the obvious one, since it has to be done under load to be worth anything

Sites that run continuously often end up with their planned electrical work in an after-hours window for this reason alone, so price it that way from the start.

Specify the records, not just the work

The record is the part you will need later, and SafeWork NSW sets out what a testing record must contain: the name of the person who carried out the testing, the date, the outcome, and the date the next testing is due. It must be kept until the equipment is next tested, permanently removed from the workplace or disposed of, and may take the form of a tag on the equipment.

A second set is worth naming too. SafeWork NSW expects safe work method statements to be kept until the work is finished and risk assessments for at least 28 days afterwards, and for at least two years where there has been an electric shock or a serious injury. Ask for those to be supplied, not merely held.

Where wiring work is carried out, the certificate matters too. The person who carries out the electrical test must submit a Certificate of Compliance for Electrical Work as soon as practical and no later than seven days after the test, and since 1 July 2026 these go through the Building Commission NSW eCert portal. Ask to be nominated so a copy reaches you automatically.

Keep the fire safety boundary clear

Where a building has a fire safety schedule, emergency and exit lighting is usually listed among its fire safety measures, and your contractor’s inspection and discharge records feed into that. The statement itself is a different instrument: Fire and Rescue NSW explains that the owner of a building having a fire safety schedule must give a copy of the fire safety statement to the Commissioner, and that an annual statement says each essential fire safety measure in it has been assessed by an accredited practitioner (fire safety), and the building inspected by one.

So make the handover explicit: your contractor keeps the logbooks current and legible, and the accredited practitioner assesses. Blurring the two is how a building reaches statement time with the testing done and nothing to show for it.

Separate planned work from defects

Planned maintenance finds faults; that is its purpose. The contract should say what happens next. Require defects to be reported with a priority against each one, quoted before work proceeds, and tracked until closed, so one raised in March is not still open in September under another job number.

Cover the tenancy that has been sitting dark

One requirement catches property and strata managers out repeatedly. In NSW, where an electrical installation has been de-energised for six months or more, a safety inspection by a qualified electrician is required before re-energising, and a certificate is given to the customer to pass to their electricity retailer. If your portfolio has vacancies that run that long, put the inspection in the schedule rather than discovering it the week a tenant wants power on.

Compare quotes on the same basis

Once the register, the intervals, the isolation window and the records are written down, quotes become comparable. Before that they are not, and the cheapest is usually the one that excluded the most. If the scope also takes in air conditioning or refrigeration, note that refrigerant handling is separately authorised – Eclipse holds ARC refrigerant trading authorisation AU35479 – and a combined contract should show the two scopes separately.

Next steps

If you cannot produce a current asset register and the last set of test results for a site, that is where to start rather than the price. Eclipse scopes planned electrical maintenance for commercial, industrial and strata sites across Sydney, and can run it alongside mechanical and security work on one schedule – see our commercial electrical services. Our office hours are Monday to Friday, 7am to 5:30pm, and we offer after-hours call-outs for commercial and industrial sites. Call Eclipse on (02) 9832 9871 or send us your site details.

Before you sign an electrical maintenance contract

  • List the boards, protective devices, plug-in equipment and emergency fittings in scope, and who owns each
  • Have intervals proposed area by area, with the reasoning, instead of one figure for the site
  • Confirm the licence or qualification behind each task in the schedule
  • Agree the isolation window and who authorises an outage
  • Require testing records, certificates and a prioritised defect list after every visit
  • Add a safety inspection for any tenancy that has been de-energised six months or more

General information only. Requirements change and depend on your site, so confirm specifics with your certifier or insurer, or ask us.

FAQ

Frequently asked questions

Something else on your mind? Call (02) 9832 9871 and talk it through with us.

What should an electrical maintenance contract include?

At a minimum: an asset register naming every board, protective device, area of plug-in equipment and emergency fitting in scope; inspection and testing intervals set per area rather than per site; the licence or qualification behind each task; an agreed isolation window; the testing records and certificates you will receive; and how defects are priced and tracked. The records are the part most often left vague.

How often does commercial electrical equipment need testing?

There is no single interval. SafeWork NSW says the frequency of inspection and testing varies with the nature of the workplace and the risks associated with the equipment, and points to AS/NZS 3760 for methods and frequency. In practice a dusty or wet area carries a shorter interval than a low-risk office, which is why a contract should set intervals area by area.

What records should my contractor hand over after each visit?

SafeWork NSW requires a record of testing that specifies the name of the person who carried out the testing, the date, the outcome and the date the next testing is due, kept until the equipment is next tested, removed or disposed of. Where wiring work is done, ask for the Certificate of Compliance for Electrical Work as well, and for a defect list with priorities.

Does an electrical maintenance contract cover the annual fire safety statement?

Not on its own. Emergency and exit lighting is usually an essential fire safety measure where a building has a fire safety schedule, and your contractor's inspection and discharge records support it. But Fire and Rescue NSW describes an annual fire safety statement as saying each essential measure has been assessed by an accredited practitioner (fire safety), and that the building has been inspected by one, so the assessment sits with that practitioner.

Can electrical maintenance be done without shutting the site down?

Some of it. A thermal scan of a switchboard has to be done with the board under load, and visual inspections and portable equipment testing can usually be scheduled around operations. But SafeWork NSW is clear that electrical work must not be carried out on energised equipment, so anything inside a board needs an isolation. That is why the shutdown window belongs in the contract rather than in a phone call on the day.

Keep reading

More from the blog

All articles

Request a quote

Tell us about the job.

Send the basics and we'll call you back to scope it. Site down after hours? Call us: after-hours call-outs are available for commercial and industrial sites.

    By sending this form you agree to our privacy policy.

    Call now Get a quote